The following solution is suggested to handle the subject “Please use the table to answer questions, SHOW WORK Consider the following work breakdown structure for questions 46-50: Duration (Days) Most Start Finish Activity Node Node Optimistic Likely Pessimi…“. Let’s keep an eye on the content below!
Question “Please use the table to answer questions, SHOW WORK Consider the following work breakdown structure for questions 46-50: Duration (Days) Most Start Finish Activity Node Node Optimistic Likely Pessimi…”
Please use the table to answer questions, SHOW WORK
Consider the following work breakdown structure for questions 46-50: Duration (Days) Most Start Finish Activity Node Node Optimistic Likely Pessimistic 50 31 70 41 35 59 34 82 41 58 32 30 5 46
What is the estimated expected (mean) time tor activity D? A 32 days B. 41 days C 44 days D. 42 days E 40 dayts 46 What is the estimated standard deviation for the critical path? A 6 days B. 5 days C. 49 days D. 3 days E. 2 days 47 48 What is the estimated expected (mean) time for project completion? A 70 days B 100 days C 106 days D 120 days E. 226 days What is the estimated slack time for activity D? A 0 days B. 10days C. 14 days D. 20 days E. 80 days 49 What is the probability that this project will be completed within 130 days? A 08413 В 09 C 09544 D 0.9772 50
Answer
Expected mean time = (Optimistic + pessimistic + 4*most likely)/6
Variance = ((Pessimistic – Optimistic)/6)^2
46.
The correct answer is E.40 Days
47.
Path available: A-C Duration => 120 Days
B-D-E duration => 106 days
Critical path is A–C
Variance of the critical path = 9+16 =25 days
Standard deviation of Critical Path A-C is sqrt(25), = 5 Days
The correct answer is “B.” 5 days
48.
Project completion time = Critical path A-C duration = 120 days
Correct answer: D. 120 Days
49.
The earliest start time for B = 0 days
The Earliest End Time of B = The Earliest Start Time of B + Duration Of B = 0+30 = 30 Days
The earliest start time for D = the earliest finish time for B = 30 days
The Earliest End Time of D = The Earliest Start Time of D + Duration Of D = 30+40 =70 days
Late Finish of E = 120 Days
Late Start of E = Late End of E – Duration E = 120 – 36 = 84 Days
Late Finish of D = Late Beginn of E = 84 Days
Slack of D = Late finish – Early finish = 84 – 70 = 14 days
Correct answer is C. 14 Days
50.
When x = 130
z = (130 – 120)/5 = 2
Probability that project will be completed within 130 days = P(Z2) = 0.9772
Correct answer is D) 0.9772
Conclusion
Above is the solution for “Please use the table to answer questions, SHOW WORK Consider the following work breakdown structure for questions 46-50: Duration (Days) Most Start Finish Activity Node Node Optimistic Likely Pessimi…“. We hope that you find a good answer and gain the knowledge about this topic of business.